Ferst Drive Realignment Project – Upcoming Construction Activities

Primary tabs

er status. Will be true when the current user * is an administrator. *

As part of the ongoing Ferst Drive Realignment Project, the following work will affect vehicular and pedestrian circulation in the areas noted below. No road closures are planned; however, traffic will be flagged through active work zones. Commuters should expect delays.  

Pedestrian and Roadway Disruptions: 

Beginning Friday, July 11 

  • The southeast corner of Fifth Street and Techwood Drive will reopen to pedestrian traffic. 
  • Demolition will begin on the southwest corner of Fifth Street and Techwood Drive. 
  • The sidewalk on the south side of Fifth Street between Techwood Drive and Fowler Street will close through July 25. 

Monday, July 14, Through Wednesday, July 23 

  • Milling operations will take place along Fifth Street and Ferst Drive, from Russ Chandler Stadium to the Fifth Street Bridge, July 14 – 16. 
  • Milling of failing sections of asphalt on Fowler Street and Fourth Street is scheduled for July 16. To facilitate this work, parking along Fowler Street will be closed July 15 – 23. Please refer to the map for parking impacts. 
  • Paving will occur along Fifth Street and Ferst Drive July 21 – 23. 
  • Paving will be completed on Fowler Street and Fourth Street on July 23. 

Status

  • Workflow status: Published
  • Created by: Rachael Pocklington
  • Created: 07/10/2025
  • Modified By: Rachael Pocklington
  • Modified: 07/10/2025

Categories

  • No categories were selected.