Price Gilbert and Crosland Tower Renewal: November 2016 through January 2020
Primary tabs
CONSTRUCTION DETAILS:
- Start Date: November 1, 2016
- Anticipated End Date: January 30, 2020
Normal Working Hours: 7am-5pm. Weekend work will only be necessary in there are major rain delays.
Campus Detours or Interruptions:
Phased detours of pedestrian traffic will occur around the Library complex, corresponding the construction sequences.
November 2016-2017: Work will close the north sidewalk of Bobby Dodd Way between Old Civil Engineering Building, Cherry Street and the alley between Old Civil Engineering building and Crosland Tower.
July 2017-November 2018: Work will close described above and also pedestrian way between Bobby Dodd Way/Cherry Street to Fourth Street between Price Gilbert and Crosland Tower. Access to Hinman and Rich will be maintained from Fourth Street but not o he north side of the Price Gilbert Library.
RENEWAL BENEFITS:
- Improved accessibility and/or ADA Compliance
- This project is an Adaptive Reuse and meets sustainability goals
- Added seating and study space for students
- New technology tools will support learning goals
USER DETAILS:
All computers, scanners, printers, study spaces and other resources in Crosland will move to Price Gilbert, also known as Library West. More information can be found at http://renewal.library.gatech.edu/