news

Campus Center Construction Updates - November - December 2019

Primary tabs

General:

*Construction traffic in this sector of campus.

*Normal working hours 6:00 AM – 5:30 PM.

Phase I Building Construction (within project fence line):

*Pre- Engineered Metal Buildings and roofing for the Café and Pavilion buildings will be erected.

*Exterior metal framing, sheathing, and waterproofing at the Exhibition Hall will continue.

*Roofing at Exhibition Hall will be substantially complete.

*Exhibition Hall masonry and window systems installation will begin.

*Overhead mechanical, electrical, and plumbing systems at the Exhibition Hall will be installed.

*Interior metal framing walls and door frames will be installed at Exhibition Hall.

Phase I Utilities:

*Storm, sanitary sewer, and power ductbank will be installed north of the Student Center Parking Garage 9/6/2019 – 12/20/2019.  Work should pass Smithgall 11/15

*Fencing will remain in place to provide barriers between construction activities and the campus.

*Signage will remain in placed around perimeter of fencing to direct pedestrian traffic. 

*Pedestrian pathways approaching Ferst Center from ISYE lawn have been installed to divert walkways around construction.

*Way finding signage has been placed around this part of campus to provide alternate routes.

*ADA pathways will be maintained from the parking lot in front of Student Services to Ferst Center for the Arts.

 

 

 

 

 

 

Status

  • Workflow Status:Published
  • Created By:cbrim3
  • Created:10/29/2019
  • Modified By:cbrim3
  • Modified:10/31/2019