Greenfield & Dalney Ductbank Installation

Primary tabs

Communication ductbanks will be installed across Dalney St. and Greenfield St. in order to re-route aerial cables to below ground.   

Construction Start Date: Monday, May 13, 2019                                                                

Tentative Construction Completion Date: Friday, July 6, 2019   

Impact:    

·        Parallel parking along Greenfield St. NW will be off-line from Monday, May 13th until Friday, May 24th.

·        Traffic heading south on Greenfield St. NW will be temporarily re-routed to the drop-off lane at the GTRI Research Building North.

·        Parallel parking along Dalney St. NW will be off-line from Monday, May 27th until Friday, June 7th.

 